CONSTRUCTION INFORMATION. Here you find an overview of construction activities during the next few weeks that may affect you on different locations on Medicinareberget, not just where blasting takes place. In December and January work in Medicinarelängan may at some times lead to increased noise. All three weeks the trucks will use the north gate close to EBM for both entry and exit. Thursday, December 12, the spare blast time at 15:00 may be used to divide some boulders. During weeks 52 and 1 the groundwork of the new premises for the Faculty of Science closes down for the holiday. If you have any questions about the construction activities, please email medicinareberget@gu.se.
WEEK 49, December 2 – 6.
Medicinareberget
LUNDBERG LABORATORY
The work on replacing ventilation units is proceeding. The crane previously seen in the passage between Medicinarelängan och Lundberglabb is now removed but will come back on occasion, possibly in December.
MEDICINARELÄNGAN LOWER FLOOR
Reconstruction is ongoing in order to prepare for docking the new building for the Faculty of Science and to provide temporary premises for Center for Cellular Imaging, CCI, who will move from 7A to Medicinaregatan 5. The work means disturbing noise particularily during hours stated below. In addition, work on venttilation will take place over the weekend December 7-8. This reconstruction work is estimated to be ready by end of January, 2020.
Hours in week 49 with increased noise disturbances:
- Dec 2, Mon 07:00-08:00, 11:30-12:30
- Dec 3 Tues 07:00-10:00, 12:00-14:00
- Dec 4 Wed 07:00-09:00, 12:00-14:00
- Dec 5 Thu 07:00-08:00, 12:00-14:00
- Dec 6 Fri 7:00-09:00, 12:00-13:00
See map for details här. (Swedish)
MODULES AT LUNDBERG LABORATORY
Modules have been put up on the parking lot outside Lundberg laboratory. They are a part of the solution for replacement premises for the functions that need to move out from Medicinarelängan. The current work focuses on installations and the interior along with the construction of a passage connecting th modules with the building. The mobile crane is removed in week 49.
New premises for the Faculty of Science
After a number of blasts close to Nya Forsken, outloading will follow in this area. The reinforcement work on the rock wall continues assisted by the excavator. Metal rods are mounted into drilled holes in the rock wall. One blast will take place on the road toward the south gate. In parallel, preparations for clearing the surface and drilling near the EBM media central are carried out. This is where major parts of the blasting in December will take place.
Blasting in week 49 will take place Tuesday and Thursday at 12.30 as usual with reserve times at 15.00 on the same days.
WEEK 50, December 9 – 13.
Medicinareberget
LUNDBERG LABORATORY
The work on replacing ventilation units is proceeding. The crane previously seen in the passage between Medicinarelängan och Lundberglabb is now removed but will come back on occasion, possibly in December.
MEDICINARELÄNGAN LOWER FLOOR
Reconstruction is ongoing in order to prepare for docking the new building for the Faculty of Science and to provide temporary premises for Center for Cellular Imaging, CCI, who will move from 7A to Medicinaregatan 5. The work means disturbing noise particularily during hours stated below. In addition, work on venttilation will take place over the weekend December 7-8. This reconstruction work is estimated to be ready by end of January, 2020.
Hours in week 50 with increased noise disturbances:
- Dec 9, Mon 07:00-12:00
- Dec 10 Tues 07:00-10:00
- Dec 11 Wed 07:00-12:00
- Dec 12 Thu 07:00-08:00, 11:00-13:00
- Dec 13 Fri 07:00-09:00, 12:00-14:00
See map for details here (Swedish).
MODULES AT LUNDBERG LABORATORY
Modules have been put up on the parking lot outside Lundberg laboratory. They are a part of the solution for replacement premises for the functions that need to move out from Medicinarelängan. The current work focuses on installations and the interior along with the construction of a passage connecting the modules with the building.
New premises for the Faculty of Science
Outloading of rock material continues along the facade of Nya Forsken. For those located in the building, it will become obvious that the ground level is lowered.
Blasting in week 50 will focus on the area around the EBM media central. The surface is cleared as preparation for the drilling.
During the week some preparation for the closing in week 52 and week 1 will be done.
Blasting in week 50 will take place Tuesday and Thursday at 12.30 with reserve times at 15.00 on the same days as usual.
The reserve time on Thursday at 15.00 might be used for dividing some large rocks to enable them to be outloaded. Prior to this blast there will be a warning signal as is the case before all blasts.
WEEK 51, December 16 – 20.
LUNDBERG LABORATORY
The work on replacing ventilation units is proceeding. The crane previously seen in the passage between Medicinarelängan och Lundberglabb is now removed but will come back on occasion, possibly in December.
MEDICINARELÄNGAN LOWER FLOOR
Reconstruction is ongoing in order to prepare for docking the new building for the Faculty of Science and to provide temporary premises for Center for Cellular Imaging, CCI, who will move from 7A to Medicinaregatan 5. The work means disturbing noise particularily during hours stated below. This reconstruction work is estimated to be ready by end of January, 2020.
Hours in week 51 with increased noise disturbances:
- Dec 16, Mon 07:00-08:00, 11:00-12:00
- Dec 17 Tues 07:00-09:00, 12:00-14:00
- Dec 18 Wed 07:00-08:00, 11:00-12:00
- Dec 19 Thu 07:00-11:00
- Dec 20 Fri 07:00-09:00, 12:00-14:00
See map for details here. (Swedish)
MODULES AT LUNDBERG LABORATORY
Modules have been put up on the parking lot outside Lundberg laboratory. They are a part of the solution for replacement premises for the functions that need to move out from Medicinarelängan. The current work focuses on installations and the interior along with the construction of a passage connecting th modules with the building.
New premises for the Faculty of Science
Work continues on level three with drilling and blasting in the area close to the EBM media central.
Apart from the area closest to Medicinarelängan, the work is getting closer to finalization of level three, the level that is in level with the surrounding ground level. After Christmas and New Year holiday the work on level four starts. This corresponds to the basement level of the new building.
Blasting in week 51 will take place Tuesday and Thursday at 12.30 with reserve times at 15.00 on the same days as usual.
In the Staff Portal you will find more information about construction projects on Medicinareberget: https://medarbetarportalen.gu.se/sahlgrenskaakademin/byggprojektmedicinareberget/