CONSTRUCTION INFORMATION. Akademiliv provides information on the construction of Natrium on Medicinareberget for the period weeks 7-10 (February 15 – March 12).
The current information about constructions on Medicinareberget is distributed with special mailings and in Akademiliv every four weeks. As far as the information mailings are planned, you will receive these mailings with information March 15, April 12, May 10, June 7 and August 16.
In regards of covid-19, there is currently no impact on the progress of the projects, but developments can change quickly. The University of Gothenburg and Akademiska Hus are closely monitoring developments and are making adjustments as needed.If you have questions about the construction activities, feel free to email medicinareberget@gu.se.
This text contains references to addresses. An updated map is available in PDF format on the Campusservice Medicinareberget web page on Medarbetarportalen via link here.
Activities on the construction site
Construction continues according to schedule. Several important milestones have been achieved, like the base construction.
In the basement, erection of the super structure is ongoing. In week 7, the first round out of in total four for the first level. In parallel, material that will be needed further on is lifted inside.
Activities inside Medicinarelängan
Demolition work inside Medicinarelängan is completed and construction is starting.
Interior walls for are being built and so is installations.