CONSTRUCTION INFORMATION. Akademiliv provides an overview of the construction project for new premises for the faculty of science and reconstruction work in Medicinarelängan and the Lundberg Laboratory. During the period, the structure-borne noise from work on floor 1000 in Medicinarelängan will cease, which means that disruptions for adjacent operations will be reduced. If you have any questions about the construction activities, feel free to email medicinareberget@gu.se.
WEEK 11, March 9 – 13.
Medicinaregatan 14 – replacement premises for parts of the Institute of Biomedicine
Due to the new construction for the Faculty of Science, preparations for replacement premises for parts of the Department of Biomedicine are ongoing. The former Akademiska Hus operating office will therefore be renovated during winter/spring of 2020.
The parking lot continues to be closed due to the construction related activities such as asphalting. The renovation is estimated to be ready beginning of April.
Here you can see a map of rebuilding at Medicinaregatan 14 (Swedish only): https://gubox.box.com/s/gyml6y92a171fm0twohmz5deuh1ziggj
Medicinarelängan lower floor – replacement premises for CCI
Reconstruction is ongoing in order to prepare for docking the new building for the Faculty of Science and to provide temporary premises for Center for Cellular Imaging, CCI, who will move from 7A to Medicinaregatan 1F.
Move of microscopes will take place in March and will temporarily effect corridor 1150. Lab furnishings will be delivered continuously during March and April. The renovation is estimated to ready beginning of April.
Here you can see a map of rebuilding CCI (Swedish only): https://gubox.box.com/s/6u26fb6e95rhxtvsvtxd75dvfnkc3k5w
Modules at Lundberg Laboratory
Delivery of lab furnishings is ongoing.
Lundberg Laboratory
Delivery of lab furnishings for the third and fourth floor is ongoing. In one half of the second floor, reconstruction has started. The work is planned to be ready by end of April.
A space between the Lundberg laboratory is used for containers (blue) and materials (red). View map with details here: https://gubox.box.com/s/g7w127ruueuoph3x9kusu8y1x71rw5ml
Natrium
The blasting work on the fourth level continues in week 11.
In the previous week, blasting for a culvert between the pit for the new building and the EBM media central. In this week, the shafts are finalized with a minor impact blast in the area close to the media central. The other blast will take place in the center of the construction site.
The week is largely characterized by preparations for the blasting on level three and four of the remaining rock in the area close to Medicinarelängan.
As a means to avoid covering the windows completely before all staff have relocated, a plank made of wood completed with semi-transparent plastic cover attached to plank and roof above it, allowing some daylight to come through will be placed close to the facade.
The surface is cleared from soil and vegetation with caution, first by an excavator and thereafter with help from compressed air.
To allow vehicles to access the area, a ramp made of rocks is put in place.
The mapping made by the geologist engineer is an activity not causing any noise. it aims for investigating cracks and the condition of the rocks in general before taking approprate decisions regarding the coming drilling, re-inforcement and blasting.
The drilling that follows is however not free from noise but the drill rig is equipped by a silencer to minimize disturbances for those working nearby.
Blasting in week 11 will take place Tuesday and Thursday at 12.30 with reserve time at 15.00 on the same days.
WEEK 12, March 16 – 20.
Medicinaregatan 14 – replacement premises for parts of the Institute of Biomedicine
Due to the new construction for the Faculty of Science, preparations for replacement premises for parts of the Institute of Biomedicine are ongoing. The former Akademiska Hus operating office will therefore be renovated during winter/spring of 2020.
The parking lot continues to be closed due to the construction related activities such as asphalting.
The renovation is estimated to be ready beginning of April.
Here you can see a map of rebuilding at Medicinaregatan 14 (Swedish only): https://gubox.box.com/s/gyml6y92a171fm0twohmz5deuh1ziggj
Medicinarelängan lower floor – replacement premises for CCI
Reconstruction is ongoing in order to prepare for docking the new building for the Faculty of Science and to provide temporary premises for Center for Cellular Imaging, CCI, who will move from 7A to Medicinaregatan 1F.
Move of microscopes will take place in March and will temporarily effect corridor 1150. Lab furnishings will be delivered continuously during March and April. The renovation is estimated to ready beginning of April.
Here you can see a map of rebuilding CCI (Swedish only): https://gubox.box.com/s/6u26fb6e95rhxtvsvtxd75dvfnkc3k5w
Modules at Lundberg Laboratory
Delivery of lab furnishings is ongoing.
Lundberg Laboratory
Delivery of lab furnishings for the third and fourth floor is ongoing. In one half of the second floor, reconstruction has started. The work is planned to be ready by end of April.
A space between the Lundberg laboratory is used for containers (blue) and materials (red). View map with details here: https://gubox.box.com/s/g7w127ruueuoph3x9kusu8y1x71rw5ml
Natrium
The Tuesday blast will take place in the center of the area.
In week 12, the preparations for the Thursday blast close to Medicinarelängan continues.
The surface is cleared from soil and vegetation with caution, first by an excavator and thereafter with help from compressed air. Thereafter, the drilling takes place.
Blasting in week 11 will take place Tuesday and Thursday at 12.30 with reserve time at 15.00 on the same days.
WEEK 13, March 23 – 27.
Medicinaregatan 14 – replacement premises for parts of the Institute of Biomedicine
Due to the new construction for the Faculty of Science, preparations for replacement premises for parts of the Institute of Biomedicine are ongoing. The former Akademiska Hus operating office will therefore be renovated during winter/spring of 2020.
The parking lot continues to be closed due to the construction related activities such as asphalting.
The renovation is estimated to be ready beginning of April.
Here you can see a map of rebuilding at Medicinaregatan 14 (Swedish only): https://gubox.box.com/s/gyml6y92a171fm0twohmz5deuh1ziggj
Medicinarelängan lower floor – replacement premises for CCI
Reconstruction is ongoing in order to prepare for docking the new building for the Faculty of Science and to provide temporary premises for Center for Cellular Imaging, CCI, who will move from 7A to Medicinaregatan 1F.
Move of microscopes will take place in March and will temporarily effect corridor 1150. Lab furnishings will be delivered continuously during March and April. The renovation is estimated to ready beginning of April.
Here you can see a map of rebuilding CCI (Swedish only): https://gubox.box.com/s/6u26fb6e95rhxtvsvtxd75dvfnkc3k5w
Modules at Lundberg Laboratory
Delivery of lab furnishings is ongoing.
Lundberg Laboratory
Delivery of lab furnishings for the third and fourth floor is ongoing. In one half of the second floor, reconstruction has started. The work is planned to be ready by end of April.
A space between the Lundberg laboratory is used for containers (blue) and materials (red). View map with details here: https://gubox.box.com/s/g7w127ruueuoph3x9kusu8y1x71rw5ml
Natrium
Week 13 will be similar to week 12.
The outloading of rock from the construction site continues and amounts to 1000 tons of rock daily.
Blasting in the week will take place Tuesday and Thursday at 12.30 with reserve time at 15.00 on the same days.
The Tuesday blast takes place in the center of the area while the Thursday blast will be close to Medicinarelängan.
In the Staff Portal you will find more information about construction projects on Medicinareberget: https://medarbetarportalen.gu.se/sahlgrenskaakademin/byggprojektmedicinareberget/