BUILDING INFORMATION. Akademiliv provides an overview of the construction project for new premises for the faculty of science and reconstruction work in Medicinarelängan and the Lundberg Laboratory. Rebuilding of replacement premises may continue to cause disturbing noise. During this period, rebuilding on the 2nd floor in Lundberg lab will commence, which will start with demolition and removal. If you have any questions about the construction activities, feel free to email medicinareberget@gu.se.
WEEK 7, February 10 – 14.
Medicinaregatan 14 – replacement premises for parts of the Institute of Biomedicine
Due to the new construction for the Faculty of Science, preparations for replacement premises for parts of the Institute of Biomedicine are ongoing. The former Akademiska Hus operating office will therefore be renovated during winter/spring of 2020.
The parking lot continues to be closed during weeks 7-9 due to construction related activities such as asphalting.
Here you can see a map of rebuilding at Medicinaregatan 14 (Swedish only): https://gubox.box.com/s/k17wqpzfl66uljgc58c4hxqm36s78nr0
Medicinarelängan lower floor – replacement premises for CCI
Reconstruction is ongoing in order to prepare for docking the new building for the Faculty of Science and to provide temporary premises for Center for Cellular Imaging, CCI, who will move from 7A to Medicinaregatan 5.
Move of microscopes will take place on February 10 and will temporarily effect corridor 1150. Lab furnishings will be delivered continuously during March and April.
The work means disturbing noise particularly during hours stated below.
- Mon Feb 10, 7:00-8:00
- Tue Feb 11, 7:00-08:00
- Wed Feb 12, 7:00-9:00, 12:00-13:00
- Thu Feb 13, 7:00-9:00, 11:00-13:00
- Fri Feb 14, 7:00-8:00
Here you can see a map of rebuilding CCI (Swedish only): https://gubox.box.com/s/6s3uohqnpk0jtzum6fjorn45b338hawl
Modules at Lundberg Laboratory
The exterior is being restored and tidied up and this will take a few weeks.
Lundberg Laboratory
Lab furnishings for the third and fourth floor are not yet in place. The deliveries will be carried out through the rear entrance but are not likely to cause any disturbances for pedestrians.
Reconstruction on the second floor will possibly be initiated in this three-week period, starting with demolition. Material will be delivered through the walkway between Medicinarelängan and the Lundberg laboratory.
New premises for the Faculty of Science (Natrium)
The construction site is being restored after the successful starting ceremony held last week.
The groundwork outside the facade of Nya Forsken that was announced in the latest newsletter has been postponed two weeks.
Inside the fence close to EBM, work is ongoing to move rocks and soil to even out the surface to create unloading zones and storage of material.
The blasting and outloading continues going from EBM in the direction toward Nya Forsken. See image for details. The trucks enter and exit the site mostly through the gate close to Medicinaregatan 1.
Blasting in week 7 will take place Tuesday and Thursday at 12.30 with reserve time at 15.00 on the same days.
WEEK 8, February 17 – 21.
Medicinaregatan 14 – replacement premises for parts of the Institute of Biomedicine
Due to the new construction for the Faculty of Science, preparations for replacement premises for parts of the Institute of Biomedicine are ongoing. The former Akademiska Hus operating office will therefore be renovated during winter/spring of 2020.
The parking lot continues to be closed during week 7-9 due to construction related activities such as asphalting.
Here you can see a map of rebuilding at Medicinaregatan 14 (Swedish only): https://gubox.box.com/s/k17wqpzfl66uljgc58c4hxqm36s78nr0
Medicinarelängan lower floor – replacement premises for CCI
Reconstruction is ongoing in order to prepare for the docking of the new building for the Faculty of Science and to provide temporary premises for Center for Cellular Imaging, CCI, who will move from 7A to Medicinaregatan 5.
Lab furnishings will be delivered continuously during March and April.
The work means disturbing noise particularly during hours stated below.
- Mon Feb 17, 7:00-8:00
- Tue Feb 18, 7:00-8:00, 12:00-13:00
- Wed Feb 19, 7:00-9:00,
- Thu Feb 20, 7:00-9:00 12:00-13:00
- Fri Feb 21, 07:00-09:00, 12:00-13:00
Here you can see a map of rebuilding CCI (Swedish only): https://gubox.box.com/s/6s3uohqnpk0jtzum6fjorn45b338hawl
Modules at Lundberg Laboratory
The exterior is being restored and tidied up and this will take a few weeks.
Lundberg Laboratory
Lab furnishings for the third and fourth floor are not yet in place. The deliveries will be transported through the rear entrance but are not likely to cause any disturbances for pedestrians.
Reconstruction on floor 2 will possibly be initiated in this three-week period, starting with demolition. Material will be delivered through the walkway between Medicinarelängan and the Lundberg laboratory.
New premises for the Faculty of Science (Natrium)
In week 8 the groundwork close to the facade of Nya Forsken will start. (See blue mark in image) This activity needs caution and is partly carried out by an excavator and partly manually, to lay bare cables under the soil.
Blasting takes place behind the EBM media central. This means that the final level of the road gets defined.
Blasting in week 8 will take place Tuesday and Thursday at 12.30 with reserve time at 15.00 on the same days.
WEEK 9, February 24– 28.
Medicinaregatan 14 – replacement premises for parts of the Institute of Biomedicine
Due to the new construction for the Faculty of Science, preparations for replacement premises for parts of the Institute of Biomedicine are ongoing. The former Akademiska Hus operating office will therefore be renovated during winter/spring of 2020.
The parking lot continues to be closed during week 7-9 due to construction related activities such as asphalting.
Here you can see a map of rebuilding at Medicinaregatan 14 (Swedish only): https://gubox.box.com/s/k17wqpzfl66uljgc58c4hxqm36s78nr0
Medicinarelängan lower floor – replacement premises for CCI
Reconstruction is ongoing in order to prepare for docking the new building for the Faculty of Science and to provide temporary premises for Center for Cellular Imaging, CCI, who will move from 7A to Medicinaregatan 5.
Move of mocroscopes will take place on February 24 and this will temporary effect corridor 1150.
Lab furnishings will be delivered continuously during March and April.
The work means disturbing noise particularly during hours stated below.
Hours in week 9 with increased noise disturbances:
- Mon Feb 24, 7:00-9:00, 12:00-13:00
- Tue Feb 25, 7:00-9:00
- Wed Feb 26, 07:00-09:00
- Thu 27, 07:00-09:00
- Fri 28, 07:00-09:00
Here you can see a map of rebuilding CCI (Swedish only): https://gubox.box.com/s/6s3uohqnpk0jtzum6fjorn45b338hawl
Modules at Lundberg Laboratory
The exterior is being restored and tidied up and this will take a few weeks.
Lundberg Laboratory
Lab furnishings for the third and fourth floor are not yet in place. The deliveries will be transported through the rear entrance and is not likely to cause any disturbances for pedestrians.
Reconstruction on the second floor will possibly be initiated in this three-week period, starting with demolition. Material will be delivered through the walkway between Medicinarelängan and the Lundberg laboratory.
New premises for the Faculty of Science (Natrium)
In week 9, drilling and blasting takes place in the center of the construction site. The outloading is up to the usual speed and both enters and exits through the gate close to Medicinaregatan 1.
Blasting in the week will take place Tuesday and Thursday at 12.30 with reserve time at 15.00 on the same days.
In the Staff Portal you will find more information about construction projects on Medicinareberget: https://medarbetarportalen.gu.se/sahlgrenskaakademin/byggprojektmedicinareberget/