In February this year the blasting started close to Medicinarelängan and has not gone unnoticed among those close to the location. Blasting has come quite far now and is currently carried out on level three out of four in total. Each level has a height of approximately five meters. Since February, the construction site has been in preparation for the planned new construction. In the surrounding area trucks are seen going in and out through the gates. Currently five trucks are engaged in the outloading. Each truck takes carries away ten full loads a day. Recently a milestone was reached with 100 000 tons of rock material outloaded so far.